Where resource efficiency is concerned, bigger is certainly not always better! |
Capacity is such a vital aspect
of manufacturing success that it is not unusual to find industrial sites where
equipment is far bigger than it needs to be. Part of the reason for this is the
need for production plants to be flexible, in which case excess capacity is
probably justifiable. It is also often the case that over-sized equipment is
installed with an eye on future expansion. The thinking in this case is that
the slack will eventually be taken up. Then of course there is the case of
the "prudent" engineer, who installs over-sized equipment simply to be absolutely sure that
required production levels are reliably met. This “just in case” approach is in my experience probably the most prevalent reason for the large
amount of over-sized equipment I come across.
Specifying equipment that is too
large for the duty obviously incurs unnecessarily large capital costs. But a
far more insidious impact is the inefficient manner in which oversized
equipment consumes resources. When you consider that the life cycle costs associated with
most process equipment are typically dominated by the costs of resource
consumption rather than the initial capital outlay, it is easy to see how what
seems like a prudent capacity decision at the time of purchase can have seriously
detrimental impacts on profitability.
In general, equipment tends to
operate best at the capacity level for which it was designed. To illustrate
this point, let’s look at a few examples of oversized equipment and explore the
impact of operating them at capacity levels significantly below design ratings.
CASE 1: UNDER-LOADED INDUCTION MOTORS
Induction motors have a nameplate
capacity that determines the amount of shaft power they develop when under full
load. The input power to the motor under full-load conditions may be estimated
by dividing the rated capacity by the full-load efficiency of the motor. Hence,
as an example, a 7.5kW motor with a full-load efficiency of 88.6% would have an
input power at full load of 7.5 kW / 88.6% = 8.47kW.
Motors rarely operate under full
load for extended periods of time. The loading of a motor may be assessed by
measuring input power and then dividing it into this full-load input power
figure.
Motor loading = measured input
power / (Rated full-load power / ƞfull-load)
Hence, say for the 3-phase
induction motor in our example we measured the input power of the individual
phases under typical operating conditions and determined the total input power
to be 4.3 kW. The loading of this motor would then be 4.3kW / 8.47kW = 51%.
This motor would clearly be significantly under-loaded. A loading of less than
100% is not necessarily a bad thing, the key consideration is where the loading
level places the motor along its efficiency continuum.
The efficiency of an induction
motor varies significantly with load. Below is a typical induction motor
efficiency curve.
As shown, at loadings slightly below 100%, motor efficiency is actually greater than at full load. However, at low loadings, we see that motor efficiency drops off sharply. Based on this efficiency curve, running a motor at the loading we calculated above would result in the motor operating at an efficiency level of some 90% of full-load efficiency. Hence the efficiency level of the motor would be 90% x 88.6% = 79.74%. Should this particular motor operate continuously, this efficiency deficit can cause operating costs to mount up very quickly.
As shown, at loadings slightly below 100%, motor efficiency is actually greater than at full load. However, at low loadings, we see that motor efficiency drops off sharply. Based on this efficiency curve, running a motor at the loading we calculated above would result in the motor operating at an efficiency level of some 90% of full-load efficiency. Hence the efficiency level of the motor would be 90% x 88.6% = 79.74%. Should this particular motor operate continuously, this efficiency deficit can cause operating costs to mount up very quickly.
For this situation, it should be
clear that the use of a motor with a higher full-load efficiency than the one installed would
not solve our problem. The solution would be to specify a smaller motor, which
would mean operating at a higher loading and hence a movement up the efficiency
curve to a level closer to full-load efficiency.
Boilers are rated to deliver a
specific quantity of steam at a given temperature and pressure, using a given
fuel. At this “maximum continuous rating”, the boiler would operate at its
optimal efficiency. However, when operated at throughput levels lower than the
MCR, efficiency tends to decline. The reasons are to do with the fact that
burners and other auxiliary equipment are designed to work best over a specific
throughput range, and that shell losses, which are fixed, become a larger
proportion of the overall boiler losses at lower throughputs. In addition,
remember that boilers are heat transfer devices, and as such, reductions in the
rate of gas flow through a boiler, as happens at lower throughputs, result in
reduced heat transfer coefficients on the combustion side.
A typical boiler efficiency curve
is as indicated below.
It is clear that operating a
boiler at 30% of its design capacity can result in a significant efficiency
drop, as compared to operating it at say, 60% of its design capacity. The
difference in efficiency results in a significant increase in the amount of
fuel required to produce a given mass of steam.
Cleaning in place (CIP) refers to
the process of cleaning the product-side surfaces of processing equipment in
the food industry. This is typically accomplished by pumping water and cleaning
solutions through pipelines, or using spraying devices to distribute water and
cleaning solutions inside process vessels. The CIP set itself comprises a
series of tanks, pipelines, valves and pumps. Each tank holds an individual
solution or process fluid, such as water, acid solutions, sterilising agents, caustic
solutions or recovered rinse water. There are several ways in which an
oversized CIP set can lead to wastage of resources. Some of these could
include:
- If the tanks are too large, more fluids than are necessary will be heated and pumped for cleaning. This translates into more water, chemical and energy use than is necessary for constituting the cleaning solutions. Large tanks also translate into more heat transfer surface and hence more heat loss to the surroundings;
- If the flows employed are too high, a significant amount of energy could be wasted. Since centrifugal pumps are typically used for pumping CIP fluids, and energy consumption for these pumps varies with the cube of flowrate, small deviations in excess of minimum required flows could result in significantly more pumping energy being used;
- While CIP sets are typically designed to recover water and cleaning solutions, thereby reducing their resource consumption, some water discharge and loss of cleaning solution is unavoidable – essentially the water used for cleaning becomes too contaminated for reuse. It is also necessary to periodically drain the system and make up fresh solutions. In the case of an oversized CIP plant, the resource losses associated with ongoing operation and intermittent refreshing of cleaning fluids tends to be higher.
There are many other common
examples of oversized equipment I could cite, and in all cases, the amount of
resources they consume per unit of production is higher than it would have been
had they been correctly specified. Of course, it is not always possible to
justify the removal of equipment and its replacement with a correctly-sized
alternative, so what would the solutions to this challenge be in practical
terms?
The first approach I would
recommend would be to try to identify the drivers of the inefficiency behind
each individual process. For example, if an under-loaded boiler performs poorly
due to poor control of the air-to-fuel ratio at low throughput levels,
investigate the control system. It may be the damper valve characteristic that
is the problem, in which case use of a variable speed drive on the forced draft
fan could help to increase efficiency levels. If the driver of inefficiency for
an oversized heated vessel is the excessive surface area, look into insulation
as an option. In short, try to establish cost-effective plant modification
strategies as far as possible.
In many cases, modifications to
the equipment itself may not be possible. For example, an under-loaded
induction motor cannot be modified and requires replacement. However, this need not be expensive. It
may be that a motor with the correct characteristics may be available elsewhere
on your site. This is one of the reasons I recommend retaining redundant motors
as spare units, even when replacements are made on the basis of installing
higher-efficiency units. Old, standard efficiency motors that are properly
loaded are more efficient than high-efficiency motors that are under-loaded, so
there are often opportunities to deploy such motors more efficiently elsewhere
should they have been replaced with more efficient alternatives. Of course, these motors need to be in good working
order.
A final approach I would recommend
would be to investigate production planning and scheduling to assess how this
may be changed to take advantage of excess capacity in ways which minimise
resource consumption. Can larger batches be produced less frequently, for
example? Is there scope to operate at higher instantaneous capacities and extend maintenance and cleaning breaks as opposed to
spreading production over longer periods while operating the facility at low throughput levels? Much of this approach comes down to
business decisions, and considerations that impact on entire supply chains.
Product characteristics also play a significant role – for example, perishable
products have to be produced as close as possible to time of sale. It is
therefore a case of intimately understanding your processes and taking
advantage of the unique opportunities on offer, on the understanding that each
facility will be different.
So, is over-sized equipment
hurting your environmental performance and bottom line? Your first step should
be to gather all capacity data for your facility, take the necessary
measurements and find out. I can almost guarantee that you will find resource efficiency opportunities in this area.
Copyright © 2013, Craig van Wyk,
all rights reserved